New Home Construction in Hillsborough, CA

Get a Free Hillsborough New Home Consultation

Custom Homes in Hillsborough

Design review: every exterior change in Hillsborough needs design review. Staff reviews minor projects; the five-member Architecture and Design Review Board (ADRB), which meets the first Monday of each month, reviews new homes and substantial additions, and new houses, major remodels and teardowns start with an ADRB preliminary review. A pre-application meeting is required, board members visit the site, and the Town mails notice to owners within 500 feet 15 days before the hearing.

Story poles are required for ADRB projects 22 feet tall or more, new two-story homes and second-story additions. They go up at least 10 business days before the hearing, are certified within 5 days, and stay up through the 15-day appeal period.

Floor area and envelope: maximum floor area is 25% of net lot area for the first acre plus 15% beyond that. Height is capped at 32 feet, with a building envelope rising 22 feet at the setback line and then sloping at 45 degrees. Setbacks are 20 feet at interior lot lines and 25 to 30 feet along streets, and the ADRB can find a home too massive even below the maximum.

Construction in Progress

Framing on new construction
Framing on new construction
Roof sheathing
Roof sheathing
Eave and fascia framing
Eave and fascia framing

Ask us about recent new-home and rebuild projects during your consultation.

New-Home Requirements

Fire sprinklers: required in all new homes, and in existing homes over 2,000 sq ft (or over two stories) when added or altered area exceeds 1,500 sq ft, or 20% for homes over 7,500 sq ft, counted over 2 years. A room counts as altered when half or more of its wall or ceiling finishes are replaced. Central County Fire, 1399 Rollins Road, Burlingame, issues sprinkler permits.

Construction rules: work hours are 8 a.m. to 5 p.m. weekdays and 10 a.m. to 5 p.m. Saturdays, with no noisy work on Sundays or Town holidays. The construction impacts ordinance covers on-site parking, screening, neighbor notice and completion time limits, and larger projects need a pre-construction meeting and a qualified superintendent.

Trees: any tree 18 inches or more in diameter at 4½ feet is protected. Removals tied to development go through design review first, with an arborist report and replanting plan.

  • Soils report for two-story homes and pier-and-grade-beam foundations.
  • Large plan check takes about 4 to 5 weeks, with site, civil, structural, energy and CALGreen sheets, a story board, materials sheet and ADRB conditions.
  • Fire-resistant construction in wildland-urban interface and high fire hazard zones.
  • Final paperwork uploaded to eTRAKiT, including special inspections, irrigation audits and professional letters.
Hillsborough Town Hall: Building and Planning
1600 Floribunda Avenue, Hillsborough, CA 94010 · Town Hall (650) 375-7400
Building (650) 375-7411, pl*******@**********gh.net · Planning (650) 375-7422 (planners by appointment) · Engineering (650) 375-7444
Applications are electronic through eTRAKiT, and contractors register with their CSLB license. Inspections are requested by phone at (650) 375-7411 at least two to three days ahead; inspectors will not inspect work by subcontractors who are not on the subcontractor list or lack a Town business license. Hours vary, so call ahead.

Explore More

Other Hillsborough services: ADUs · Bathrooms · Kitchens · Additions · Hillsborough overview

Same service nearby: Burlingame · San Mateo · Belmont

See our custom home builder page.

Hillsborough New Home Construction FAQ

Does a new home need ADRB preliminary review?

Yes, new houses and teardowns start with a preliminary review.

What is the height limit?

32 feet within the building envelope.

Are sprinklers required?

Yes, in all new homes.

What is the minimum house size?

2,500 sq ft.

Get a Free Hillsborough New Home Consultation