Bay Area ADU Permit Guide: How 13 Cities Handle ADUs

Short answer: every Bay Area city must approve a code-compliant ADU with a building permit, but each city adds its own steps. The biggest differences are size thresholds that trigger an extra Planning review, preapproved plan programs, and local site rules such as protected trees, hillside floor-area limits and septic systems. This guide summarizes what changes an ADU project in each city we build in.

Quick comparison

City Key rule that shapes most projects Preapproved plans
San Jose ADUs under 750 sq ft pay no school or park impact fees; ADU Ally at the Permit Center Yes
Sunnyvale New detached ADU over 800 sq ft needs a Miscellaneous Plan Permit first Plans Gallery
Mountain View No planning permit; all-electric Reach Code; survey before foundation near property lines Yes
Palo Alto Protected trees, flood zones and historic status drive placement —
Cupertino Valley Floor vs. hillside zoning; AC sound rating worksheet Valley Floor only
Los Altos Ministerial approval; 16 ft height for detached units —
Los Altos Hills Septic capacity, development-area (MDA/MFA) worksheets, geotechnical report —
Los Gatos Hillside floor area based on slope-adjusted lot area; historic homes —
Saratoga Height and size depend on placement inside or outside setbacks; fee waivers for affordable units —
Campbell Conversion ADU + junior ADU + detached ADU on one lot; sample plan sets Sample sets
Santa Clara Detached size depends on the 5,500 sq ft lot line; two-story designs possible —
Milpitas Over 800 sq ft needs a minor site development permit; ADU Monday consultations Yes
San Mateo Daylight plane; solar required on new detached ADUs Guide

City by city

San Jose

First-round building review typically takes about 20 business days, and complete plans usually finish in one or two review cycles. Every ADU gets its own address. The city also runs an AB 2533 program to legalize ADUs and junior ADUs built without permits. San Jose ADU details.

Sunnyvale

A new detached ADU of 800 sq ft or less stays on the building-permit-only path; larger units need a Miscellaneous Plan Permit first. A single-family lot can have up to three units in total. Sunnyvale ADU details.

Mountain View

No planning permit is required. New construction is designed all-electric under the Reach Code, and a site survey is required for structures within 6 ft of a property line before the foundation pour. The preapproved program lists an initial plan check of about 7 business days. Mountain View ADU details.

Palo Alto

Removing a protected tree requires replacement under the Tree Technical Manual, so units are usually placed around root zones. In flood zones, ADUs do not get the height extensions the main house may get. Palo Alto ADU details.

Cupertino

Preapproved detached plans apply only on Valley Floor Zone parcels. Applications need a boundary survey and, with an outdoor HVAC condenser, an AC sound rating worksheet. Cupertino ADU details.

Los Altos and Los Altos Hills

Los Altos approves compliant ADUs ministerially with a 16 ft height limit for detached units. In Los Altos Hills, homes on septic need County Environmental Health sign-off first, and the Town reviews development-area and floor-area worksheets at a pre-application meeting. Los Altos Hills ADU details.

Los Gatos and Saratoga

In Los Gatos hillside zones, the allowed ADU floor area depends on slope-adjusted lot area. In Saratoga, height and size depend on whether the unit sits inside or outside the required setbacks, and fees are waived for deed-restricted affordable ADUs. Los Gatos · Saratoga.

Campbell, Santa Clara and Milpitas

Campbell allows a conversion ADU, junior ADU and detached ADU together. Santa Clara sets detached size by lot size and offers expedited review for a fee. Milpitas offers free ADU Monday consultations and a legalization program. Campbell · Santa Clara · Milpitas.

San Mateo

There is no fixed maximum size, but the ADU must be smaller than the main home, and new detached ADUs must include solar. Compliant units need only a building permit. San Mateo ADU details.

Coming in 2027: two detached ADUs

State law AB 956 allows two new detached ADUs on a single-family lot. Read our AB 956 explainer.

Get a free site assessment

Axiom Renovation Inc. (CA License #1105006) designs, permits and builds ADUs across these cities from our San Jose office. Rules change, so we confirm the current standards for your parcel at the site visit. Bay Area ADU builders · 408-702-2022.

Facebook
Pinterest
Twitter
LinkedIn

Related Article